Progress from the past 7 days...

Administration

  • We have had 2 team calls to discuss progress
  • Started using Lighthouse to record task progress
  • Written RIPE application for temporary address space (/21 of v4 and /48 of v6) and ASN, Goscomb will be submitting this for us.
  • Recorded a kit list of what we know we have to hand

Solution design

  • Documented 4 possible scenarios

Suppliers

  • Wrote to data centre CTO, also 2 engineers, got feedback this evening that it is looking postive for roofspace and L2 circuit.
  • Contacted 7 point to point wireless suppliers to requests quotes for backhaul from the site to the datacentre (300mbps to 1gbps)
  • Written to a network supplier regarding loan kit
  • got in contact with FTTP supplier and got more details about costs and timescale.
  • artag to have a look at the 30m mast with a view to picking it up.
  • artag has seen mast, it's huge, about 5 x 1.5m
  • https://secure.flickr.com/photos/23312780@N04/7242652296/in/photostream

Waiting on

  • Confirmation from data centre
  • Quotes to come back from ptp suppliers
  • RIPE to send through details of allocated subnets