Internet/Reports/2012-05-21
From Electromagnetic Field
< Internet
Progress from the past 7 days...
Administration
- We have had 2 team calls to discuss progress
- Started using Lighthouse to record task progress
- Written RIPE application for temporary address space (/21 of v4 and /48 of v6) and ASN, Goscomb will be submitting this for us.
- Recorded a kit list of what we know we have to hand
Solution design
- Documented 4 possible scenarios
Suppliers
- Wrote to data centre CTO, also 2 engineers, got feedback this evening that it is looking postive for roofspace and L2 circuit.
- Contacted 7 point to point wireless suppliers to requests quotes for backhaul from the site to the datacentre (300mbps to 1gbps)
- Written to a network supplier regarding loan kit
- got in contact with FTTP supplier and got more details about costs and timescale.
- artag to have a look at the 30m mast with a view to picking it up.
- artag has seen mast, it's huge, about 5 x 1.5m
- https://secure.flickr.com/photos/23312780@N04/7242652296/in/photostream
Waiting on
- Confirmation from data centre
- Quotes to come back from ptp suppliers
- RIPE to send through details of allocated subnets