Timeline

From Electromagnetic Field
Revision as of 08:21, 13 January 2014 by Sling (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search


Update: Date for the event has been picked! (29-31 August)

T-12 months (around August 2013)

T-6 months (around February 2014)

  • Ticket sales open
  • Promo materials made (fliers, limited t-shirts)

T-4 months (around April 2014)

Deadline for orders:

  • Baseload power
  • Site lighting + scaff
  • Network equipement/services
  • Plant
    • Telehandler
    • Access equipment if reqd
  • Site facilities ordered
    • loos
    • showers
    • fencing
    • containers
    • tents

T-2 months (around June 2014)

T-1 months (around July 2014)

  • Badge production complete
  • Badge software complete and in last testing stages
  • Final timing schedule confirmed

T-2 weeks (First weeks of August 2014)

  • Program/flyers and any other printing works complete

Day -7 (around 22nd of August)

  • Occupation of site

Day 1 - 3 (Fri-Sun)

  • Event

Day 4-7

  • Teardown