Timeline

From Electromagnetic Field
Revision as of 13:11, 18 June 2013 by Paul (talk | contribs)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.


Potential dates range: mid-July to mid-September 2014

T-12 months

T-6 months (but ideally by Nov 2013)

  • Ticket sales open
  • Promo materials made (fliers, limited t-shirts)

T-4 months

Deadline for orders:

  • Baseload power
  • Site lighting + scaff
  • Network equipement/services
  • Plant
    • Telehandler
    • Access equipment if reqd
  • Site facilities ordered
    • loos
    • showers
    • fencing
    • containers
    • tents

T-2 months

  • Speakers/Workshops confirmed and booked in

T-1 months

  • Badge production complete
  • Badge software complete and in last testing stages
  • Final timing schedule confirmed

T-2 weeks

  • Program/flyers and any other printing works complete

T-1 week

  • Occupation of site

T-0

  • 08:00 gates open

T+1 week

  • Organisers finally relax

Scheduling conflicts to avoid

  • ICMP
  • Defcon?
  • Toorcamp?
  • UK Bank holidays - Monday 25 August 2014 - Summer bank holiday