Timeline

From Electromagnetic Field
Revision as of 12:31, 8 May 2013 by Will-h (talk | contribs)
Jump to navigation Jump to search


Potential date range: mid-July to mid-September 2014

T-12 months

  • Site selected
  • Date confirmed

T-6 months (but ideally by Nov 2013)

  • Ticket sales open

T-2 months

  • Power order finalised

T-3 weeks

  • Final timing schedule confirmed

T-2 weeks

  • Badge production complete
  • Program/flyers and any other printing works complete

T-1 week

  • Occupation of site

T-0

  • 08:00 gates open

T+1 week

  • Organisers finally relax

Events to avoid

  • ICMP
  • Defcon?
  • Toorcamp?