Potential date range: mid-July to mid-September 2014

T-12 months

  • Site selected
  • Date confirmed

T-6 months (but ideally by Nov 2013)

  • Ticket sales open

T-2 months

  • Power order finalised

T-2 weeks

  • Badge production complete
  • Program/flyers and any other printing works complete

T-1 week

  • Occupation of site

T-0

  • 08:00 gates open

T+1 week

  • Organisers finally relax