(Created page with "==T-12 months== * Site selected * Date confirmed ==T-6 months (but ideally by Nov 2013)== * Ticket sales open ==T-2 months== * Power order finalised ==T-1 week== * Occupati...")
 
 
(27 intermediate revisions by 7 users not shown)
Line 1: Line 1:
==T-12 months==
+
__NOTOC__
* Site selected
+
 
 +
'''Update: Date for the event has been picked! (29-31 August)'''
 +
 
 +
==T-12 months (around August 2013)==
 +
* [[Site_Search|Site selected]]
 
* Date confirmed
 
* Date confirmed
 +
* Food Vendor search begins
  
==T-6 months (but ideally by Nov 2013)==
+
==T-6 months (around February 2014)==
 
* Ticket sales open
 
* Ticket sales open
 +
* Promo materials made (fliers, limited t-shirts)
 +
 +
==T-4 months (around April 2014)==
 +
Deadline for orders:
 +
* Baseload power
 +
* Site lighting + scaff
 +
* Network equipement/services
 +
* Plant
 +
** Telehandler
 +
** Access equipment if reqd
 +
* Site facilities ordered
 +
** loos
 +
** showers
 +
** fencing
 +
** containers
 +
** tents
 +
 +
==T-2 months (around June 2014) ==
 +
* [[Speakers_List | Speakers/Workshops]] confirmed and booked in
  
==T-2 months==
+
==T-1 months (around July 2014) ==
* Power order finalised
+
* Badge production complete
 +
* Badge software complete and in last testing stages
 +
* Final timing schedule confirmed
  
==T-1 week==
+
==T-2 weeks (First weeks of August 2014) ==
 +
* Program/flyers and any other printing works complete
 +
 
 +
==Day -7 (around 22nd of August) ==
 
* Occupation of site
 
* Occupation of site
  
==T-0==
+
==Day 1 - 3 (Fri-Sun)==
* 08:00 gates open
+
* Event
 +
 
 +
==Day 4-7==
 +
* Teardown

Latest revision as of 08:21, 13 January 2014


Update: Date for the event has been picked! (29-31 August)

T-12 months (around August 2013)

T-6 months (around February 2014)

  • Ticket sales open
  • Promo materials made (fliers, limited t-shirts)

T-4 months (around April 2014)

Deadline for orders:

  • Baseload power
  • Site lighting + scaff
  • Network equipement/services
  • Plant
    • Telehandler
    • Access equipment if reqd
  • Site facilities ordered
    • loos
    • showers
    • fencing
    • containers
    • tents

T-2 months (around June 2014)

T-1 months (around July 2014)

  • Badge production complete
  • Badge software complete and in last testing stages
  • Final timing schedule confirmed

T-2 weeks (First weeks of August 2014)

  • Program/flyers and any other printing works complete

Day -7 (around 22nd of August)

  • Occupation of site

Day 1 - 3 (Fri-Sun)

  • Event

Day 4-7

  • Teardown