Potential date range: mid-July to mid-September 2014
+
'''Update: Date for the event has been picked! (29-31 August)'''
  
==T-12 months==
+
==T-12 months (around August 2013)==
 
* [[Site_Search|Site selected]]
 
* [[Site_Search|Site selected]]
 
* Date confirmed
 
* Date confirmed
 
* Food Vendor search begins
 
* Food Vendor search begins
  
==T-6 months (but ideally by Nov 2013)==
+
==T-6 months (around February 2014)==
 
* Ticket sales open
 
* Ticket sales open
 
* Promo materials made (fliers, limited t-shirts)
 
* Promo materials made (fliers, limited t-shirts)
  
==T-4 months==
+
==T-4 months (around April 2014)==
 
Deadline for orders:
 
Deadline for orders:
 
* Baseload power
 
* Baseload power
Line 27: Line 27:
 
** tents
 
** tents
  
==T-2 months==
+
==T-2 months (around June 2014) ==
* Speakers/Workshops confirmed and booked in
+
* [[Speakers_List | Speakers/Workshops]] confirmed and booked in
  
==T-1 months==
+
==T-1 months (around July 2014) ==
 
* Badge production complete
 
* Badge production complete
 
* Badge software complete and in last testing stages
 
* Badge software complete and in last testing stages
 
* Final timing schedule confirmed
 
* Final timing schedule confirmed
  
==T-2 weeks==
+
==T-2 weeks (First weeks of August 2014) ==
 
* Program/flyers and any other printing works complete
 
* Program/flyers and any other printing works complete
  
==T-1 week==
+
==Day -7 (around 22nd of August) ==
 
* Occupation of site
 
* Occupation of site
  
==T-0==
+
==Day 1 - 3 (Fri-Sun)==
* 08:00 gates open
+
* Event
  
==T+1 week==
+
==Day 4-7==
* Organisers finally relax
+
* Teardown
 
 
===Scheduling conflicts to avoid===
 
* ICMP
 
* Defcon?
 
* Toorcamp?
 
 
 
* UK Bank holidays?
 

Latest revision as of 08:21, 13 January 2014


Update: Date for the event has been picked! (29-31 August)

T-12 months (around August 2013)

T-6 months (around February 2014)

  • Ticket sales open
  • Promo materials made (fliers, limited t-shirts)

T-4 months (around April 2014)

Deadline for orders:

  • Baseload power
  • Site lighting + scaff
  • Network equipement/services
  • Plant
    • Telehandler
    • Access equipment if reqd
  • Site facilities ordered
    • loos
    • showers
    • fencing
    • containers
    • tents

T-2 months (around June 2014)

T-1 months (around July 2014)

  • Badge production complete
  • Badge software complete and in last testing stages
  • Final timing schedule confirmed

T-2 weeks (First weeks of August 2014)

  • Program/flyers and any other printing works complete

Day -7 (around 22nd of August)

  • Occupation of site

Day 1 - 3 (Fri-Sun)

  • Event

Day 4-7

  • Teardown